Dear Experts ,
I have question regarding lead time calculation my SNP
I have
Start Location : A
Destination location: B
I maintained Planned delivery time in ECC- material master as 10 days and cifed to Tlane Product procurement as 10 days
and leave empty in the transportation duration empty so the total lead time is 10 days from start location A to destination location B
now
I maintain 24 hours in Means of transport as transportation duration by truck
now the lead time is 11 days from start location A to destination location B
Now
i leave empty planned delivery time empty and maintain Means of transport duration as 48 hours
so the lead time is 2 days from A to B
does my understanding is correct or not advise please
Regards
Raj