Hello everyone,
I am trying to find a possibility to change the shelf life day in planned orders in APO PPDS. The shelf life planning is active in product master, where the shelf life data is maintained. The issue is that often have to pre-produce and put the produced quantities on storage under minus 25 degrees so the quality remains for even longer than a year, which means produce sometime months ahead before the requirements come in. the shelf life of the batches is then of course expired as we normally have around 50 days of shelf life. Therefore the production planning requires that they can change manually the shelf life day in planned orders in APO PPDS.
By now I could not find any heuristic / algorithm or user exit / BADI that would solve the problem.
we are using APO 7.03
I appreciate all good input.
thanks in advance!
br,
Wojciech