Hi,
I have the following scenario setup for SNP Heuristics.
Source : S1, S2
Destination : D0
T-Lanes are All Product valid from years 2012 - 9999
T-Lane : S1 -> D0 : 0hr Duration
T-Lane : S2 -> D0 : 144 hr Duration
Inbound Quota Arrangements at D0 - 100% to Partner Location S2 ( no quota for source S1)
When I run Location Heuristic in Data View for a demand 2 days from current day, it is sourcing from S1 even though I have 100% Quota arrangement to source it from S2. Is this correct?
Regards