Planned Independent Requirements are not transfered in APO

$
0
0

Dear friends,

 

I have an issue that I need to solve asap and it is related to planned independent requirements not transfered into APO.

 

The  integration models are active for material, plant, PIR, etc.

I,ve looked in application log (trx /sapapo/C3) to see if there are any errors, and there are not.

 

The initial planning strategy from ERP was customed, Z1 and it had no mapping in the APO. I think I need to create that in APO also.

But for testing purposes, I ve changed to standard.

 

The planning strategy from ERP is 40 and the one from APO is 20. (is it normal that after I reactivate the integration model for this material, the requirement stategy 20 is getting deleted and I have to put it manually ? )

 

Consumtion mode is 2 with 30 days back and forth.

 

Production storage location is 3200 - it has stock on it.

 

Does anybody have an idea regarding the issue ?

 