We have a BOM structure where Sub-Assembly is feeding into
Phantoms which finally makes Finished Goods. Here there will be 2 planned
orders, 1 for Sub-Assembly and 1 for Finished Goods. Requirement is to use
“forward scheduling with earliest date possible”. When I do that both Planned
Orders are taking the earliest date without considering the availability of
Sub-Assembly.
For making things easier, here is the example
Case 1 is the result I am getting and Case 2 is what I need,
but I can only achieve that with “backward scheduling with current date”. Does
anyone know how to get that with forward scheduling? I played around with
various settings in strategy profile but couldn’t achieve. Please help me.