Dear Experts
we met a BAPI function issue regarding PPDS Operation.confirmation from Legal Non-SAP system.
scenario is as following:
we want to build the interface between PPDS and non-SAP system, regarding OP. and order confirmation inbound processing.
now we input simulated inbound date and test using BAPI: BAPI_MOSRVAPS_CONFOPRMULTI
but we find a problem, even we set different value for fields ‘ duration’ in function. after call BAPI, It didn't reflect the 'net duration' or 'remaining duration', these fields not changed through check in Tcode:/SAPAPO/RRP3 for single operation.
In the meanwhile , but it works for fields 'confirmed Yield' and fields 'confirmed Scrap' for single operation.
my questions is that: if we need to synchronize the operation confirmation( including confirmed yield,confirmation scrap, duration),do we use the correct BAPI for this or do we need an additional BAPI, please hints.
Thanks a lot! any feedback would be welcome!
Best Regards
Kevin