Consuming Confirmed STR based on STO

$
0
0

Hi Experts,

 

Due to some difficulties, I am deviating from the SAP standard.

 

I am doing SNP planning based on Heuristics tool.

 

In my scenario, a Stock Transfer Order is created based on the completion of a production order. STO is created in reference to Production Order. During the day, whenever a production order is completed, at the same time STO is also created. Please note that STO is created based on production order and not based on confirmed STR.

 

So, automatic consumption of confirmed STR based on Stock Transfer Order doesn't help here or work here. So, is there any possibility to achieve this automatic consumption? STO created without any reference to confirmed STR in ERP.

Like whenever a STO is created, the confirmed STR's should be consumed using FIFO logic (STO consumes the first confirmed STR and then the next). And if, STO is larger than the quantity of confirmed STR, then the first confirmed STR to be consumed and then the next (until the STO quantity is completely consumed by the existing confirmed STRs).

 

If it is not possible to do via standard, I am planning to achieve this using the enhancement of CIF inbound logic of APO (Custom development ). But if I do this, the pegging relationship between the Production Order and confirmed STR, should it be retained? Or will the pegging relation to the confirmed STR is automatically lost if production order is completed?

 

Thanks,

Suresh