Hi Team,
Please for your help for the below issue in SNP CTM.
we have two plants for finished product one location (x) and semi finished items location is Y..when we are creating orders in the location x and if there is not stock..planned order should create in Y...
But when we are running heuristics in /n/sapapo/sNP94 it is creating correctly..but when we are running CTM planning, the distribution receipt is creating after 10 days... but if we can stock in stock Y then the distribution receipt is creating correctly..
Any idea why is happening ? thank