Hello Experts:
I have a business request to release the Production Planned KF from SNP into a frozen MPS (or even an inactive fcst version) in R/3. Since we have only released a forecast from the DP side to R/3 in the past, can anyone tell me the best practice to release from SNP to R/3? Do I need to create an info cube to perform the release?
The business runs a Heuristic in SNP at the finished good level and the makes modifications and would like to release this to be used in the R/3 MRP run for some groups of materials, as opposed to releasing the forecast for MRP to run on.
Currently, I can send the data from SNP Production Planned KF to a time series KF in DP and release to MD63 from there, but they would like to release directly from SNP in the future.
Any suggestions are greatly appreciated!