Hi ,
There is a capacity overload at specific resource.I extracted the production list report which shows which orders were using these resources.Some 4-5 order were observed, I have noticed that for one order the bucket capacity consumption is showing much higher than what expected.I have calculated by formula ( Dur(v) from Mode PDS / Base qty from that operation in which the resource exist * Receipt qty ) .For all other orders that calculation is correct but for the issue order I could not find the root cause.
The resource we are using is a single mixed resource with finite scheduling checked,Resource utilization is 100 %.
Please suggest what are the reasons the capacity can overload and why the bucket consumption is showing for higher for specific order.
Regards
Debasis nanda